In June I decided to start the new
pond. For this I took some vacations in June. But it was a very unlucky time. First
I contract with a machine that failed to come, because it had a damaged part.
I contract another machine, but it was already with one day of delay. I thought,
I could gain this day, but the machine had difficulty in moving and the driver
was really bad and let me with a war zone in hands. Moreover it dug more than what
I had in mind and in the project, increasing problems. Well, the pond was much
bigger. A great lesson that I had learn in the pass pay is dividends. I had much
more liner then the initial measures. But the ideal job is to make the hole
first and buy the liner later.
Then I contract two men to help me,
but they didn't appeared. Second day of delay. The things really started to run badly. Finally I
arrange only one man, instead of the two, I need to help me. When we start the
work we only could do it, for one day and half. A real heavy rain start and we
couldn't work any more. After the rain stops I had to go to work so we only
could work during week-ends.
|